5.3

Showing comments and forms 1 to 2 of 2

Comment

Community Infrastructure Levy - Draft Charging Schedule (Nov 2014)

Representation ID: 1811

Received: 12/12/2014

Respondent: Cogent Land LLP (Cogent)

Representation Summary:

Reviewing CIL
As above, our comments in respect of this are unchanged from our PDCS response.

Comment

Community Infrastructure Levy - Draft Charging Schedule (Nov 2014)

Representation ID: 1816

Received: 12/12/2014

Respondent: Cogent Land LLP (Cogent)

Representation Summary:

Moving forward, Cogent is open to a meeting with SSBC and their advisors to discuss the approach taken and to discuss common ground in advance of the submission of the DCS for Examination. To this end, we would like to reserve the right to be heard at Examination and to be notified when:
i)The DCS is submitted to the Examiner in accordance with Section 212 of the PA 2008;
ii)The recommendations of the Examiner and the reasons for these recommendations are published; and